Rice Solar Energy Project
Documents and links:
- Final Environmental Impact Statement / Plan Amendment (pdf - 6 MB)
- CEC Commission dcision (pdf - 13 MB)
- CEC Staff Assessment and Draft Environmental Impact Statement (pdf - 44 MB)
Images:
Videos:


The plant is owned by Rice Solar, a wholly owned subsidiary or SolarReserve LLC
The plant is expected to be operational by June, 2016.
California Energy Commission has approved Application for Certification on December, 2010. Construction must commence within five years from approval date.
First PPA was signed with PG&E on 2009 and approved by CPUC on 2010
An amendment to the PPA, due to changes in the interconection point and a change of the guaranteed commercial operation date from October 2013 to June 2016, was approved by CPUC on 2013
*CPUC: California Public Utilities Commission
*PPA: Power Purchase Agreement
*PG&E: Pacific Gas & Electric (utility)